[BizHanKook] Hyosung Heavy Industries has purchased the site for a complex development project in Jamwon-dong, Seocho-gu, Seoul, for 254.9 billion won. This action is a debt recovery measure following the company’s assumption of 346.4 billion won in project financing (PF) debt from the developer after failing to meet the responsible completion deadline. The land had previously failed to find a buyer through five consecutive public auctions. With this acquisition, Hyosung Heavy Industries has now secured both the newly constructed building and the land itself.

According to the construction industry, Hyosung Heavy Industries purchased the 2,492㎡ site for the Jamwon-dong complex development project for 254.9 billion won on the 20th. This purchase came immediately after five public auctions conducted by Hana Asset Trust between the 9th and 19th all ended without a bidder. The minimum bid price, which was initially 357.6 billion won, had dropped to 254.6 billion won, falling below the appraisal value (256.7 billion won). Hyosung Heavy Industries bought the land via a private contract the day after the final auction failed. The purpose of the acquisition stated in the public disclosure is "debt recovery."
The root of the situation was the failure to meet the responsible completion obligation. The developer, Jamwon-dong Complex Development PFV, pursued the new complex construction project after receiving a PF loan with a limit of 363 billion won in May 2023. The contractor, Hyosung Heavy Industries, was required to fulfill its responsible completion obligation by July 31, but failed to meet the deadline. Consequently, it assumed approximately 346.4 billion won in PF debt from the developer on August 1. This amount is 4.6 times the total contract value (74.7 billion won) for the Jamwon-dong complex construction project.
The two sides hold conflicting views on the cause of the delay in responsible completion. The developer reportedly points to issues regarding the construction of parking lot ramps and remedial works. On the other hand, Hyosung Heavy Industries maintains that the developer delayed completion by withdrawing its application for occupancy approval. The building received occupancy approval on September 4, which is 35 days past the responsible completion deadline. Consisting of 8 basement levels and 12 floors above ground (with a total floor area of 26,500㎡), Hyosung Heavy Industries completed the preservation registration of ownership that same month.
The remaining issue is how much of the debt can be recovered. Hyosung Heavy Industries plans to offset the 254.9 billion won land purchase price against the existing 346.4 billion won PF debt and cover the remainder with the value of the newly constructed building it has already secured. The difference between the assumed debt and the land purchase price is approximately 91.5 billion won. Separately, it is reported that Hyosung Heavy Industries has also failed to receive several billion won in additional construction costs. The actual scale of funds recovered will likely depend on future leasing or sales performance.
Hyosung Heavy Industries has assumed PF debts multiple times in the past. In the Oncheon-dong, Busan, residential-commercial project in December 2024, the company paid off 103.8 billion won in developer PF debt before the responsible completion deadline. In January and February of the following year, it assumed 43.6 billion won and 138.9 billion won in debt, respectively, for projects in Sincheon-dong, Daegu, and Sang-dong, due to failing to meet completion deadlines. The total debt assumed across these three sites amounts to 286.3 billion won according to disclosures.
The Jamwon-dong complex is currently difficult to sell due to an ownership dispute. The developer, Jamwon-dong Complex Development PFV, has filed for an injunction to prohibit the disposal of the property, demanding the cancellation of the ownership preservation registration held by Hyosung Heavy Industries. The Seoul Central District Court granted this request on the 8th of last month, prohibiting all disposal activities including the sale, gifting, and the establishment of jeonse rights, mortgages, or leasehold rights on the building. Hyosung Heavy Industries filed an objection to the injunction on the 2nd and is currently pursuing appeal procedures.
A Hyosung Heavy Industries official stated, "We originally participated in the project for construction profit, but the developer withdrew the occupancy approval application, causing us to miss the responsible completion deadline and eventually forcing us to assume the PF debt." The official added, "It is currently difficult to sell the building due to the injunction. We have already leased some space and plan to secure profits and reduce the burden of financial costs through additional leasing."
BizHankook contacted the legal representative of Jamwon-dong Complex Development PFV to confirm the background of the injunction filing and future litigation plans, but received no response.