[BizHanKook] It has been confirmed that DL E&C has filed a lawsuit against Cha Jun-young, Chairman of Nexplan, to demand the fulfillment of a guarantee obligation amounting to 61.1 billion KRW. Chairman Cha is the former CEO of City One, the developer of the Tongil Dongsan Condominium project in Paju, Gyeonggi Province. This litigation is understood to be related to debts incurred from the Tongil Dongsan project. DL E&C previously secured a final court ruling ordering the payment of approximately 522.9 billion KRW in a lawsuit against City One for construction costs and other claims.

According to Bizhankook’s reporting, DL E&C filed the lawsuit for the fulfillment of the guarantee obligation against Chairman Cha last April. The litigation value is 61.072 billion KRW, which is effectively the same as the accrued construction costs finalized in the Tongil Dongsan construction cost lawsuit last July. The court of first instance ruled that City One must pay 61.07207 billion KRW, an amount derived from approximately 117.2 billion KRW in accrued construction costs minus offset claims for damages related to defects.
The dispute between the two parties originated from the Paju Tongil Dongsan Condominium development project. City One and Daelim Industrial (the predecessor to DL E&C) signed a construction contract worth approximately 412.5 billion KRW in December 2006 and broke ground the following year. However, due to the 2008 global financial crisis and the real estate market downturn, the pre-subscription rate for the condominiums reached only 9%. In December of that year, Daelim Industrial halted construction at a 33% completion rate. The project has not been resumed since.
In August 2020, approximately 12 years after halting construction, Daelim Industrial filed a lawsuit for construction costs. The company demanded payments from City One, including accrued construction costs, reimbursement for bank loans it had paid off on City One’s behalf, and direct loans provided to the developer. Conversely, City One filed a countersuit, claiming that Daelim Industrial violated its obligation for "responsible completion" and demanded damages for the work stoppage as well as the demolition of the unfinished buildings. Both sides engaged in a legal battle over who was responsible for the stoppage.
The court ruled that Daelim Industrial’s suspension of work was justified. In September 2024, the court of first instance ordered City One to pay DL E&C approximately 518.4 billion KRW. In February of this year, the appellate court dismissed City One’s appeal and recognized an additional 4.5 billion KRW in reimbursement claims. The Supreme Court dismissed City One’s appeal in July, finalizing the lower court's ruling. The court reasoned that halting construction was a legitimate refusal of performance given the difficulty in receiving regular payment for the work.
Chairman Cha Jun-young served as the CEO of City One during the early stages of the Tongil Dongsan development project. According to the corporate registry, he served as the CEO of City One (then CIT Land) from February 2006 to July 2007. At the time, he was also the largest shareholder of CIT Construction and CIT Industrial Development (now Nexplan), which each held a 20% stake in City One. By the end of 2018, he became the largest shareholder with a 30% stake in City One, but his name was removed from the shareholder list the following year.
Given City One’s financial condition, it will not be easy for DL E&C to recover its claims. As of the end of last year, City One had assets of 133.2 billion KRW but liabilities reaching 637.9 billion KRW, resulting in total capital impairment. Due to the departure of key personnel and inadequate accounting records, the external auditor issued a disclaimer of opinion on the 2025 financial statements. Prior to this lawsuit, DL E&C had already filed for a provisional seizure of Chairman Cha’s shares in Nexplan, which was granted by the court.
A DL E&C official stated, "Considering City One's financial status, it appears that recovering the debt will take a considerable amount of time," adding, "We are currently exploring various methods for debt recovery."
A Nexplan official commented regarding the lawsuit, "We have no position to share at this moment."