KF-21 Production Unit 1 Successfully Completes First Flight Just 22 Days After Rollout

This article was automatically translated by AI. There may be errors compared to the original Korean article.  Read original in Korean →

[비즈한국] The KF-21 Boramae fighter jet, which was rolled out on March 25th, successfully completed its first flight on April 15th. This milestone was achieved just 22 days after the rollout ceremony, a result that can be considered unparalleled when compared to international precedents. While Korea Aerospace Industries (KAI), the Defense Acquisition Program Administration (DAPA), and the Air Force reportedly celebrated the first flight quietly without a large event, this achievement is expected to garner significant attention from potential overseas customers as another accomplishment of the KF-21 development project, which is proceeding at an unprecedented speed and schedule.

First flight of KF-21 production unit 1. Photo=@aero_thyhoon K1 Instagram
First flight of KF-21 production unit 1. Photo=@aero_thyhoon K1 Instagram

According to reports, the first KF-21 production unit took off from the 3rd Flying Training Wing in Sacheon on April 15th and successfully conducted its initial flight for a set period. Following the rollout ceremony on March 25th, no specific details had been announced other than its planned delivery to the Air Force by the end of the year. It appears that no public commemorative event was held due to the extremely short interval between the rollout and the first flight.

The fact that it took only 22 days from the rollout to the first flight is another achievement that demonstrates the technical maturity of the KF-21, much like the 1,600 accident-free test flights completed successfully over the past three years. This is because it represents an "unrivaled speed" that has no comparison among fighter jet deployment schedules over the last 30 years.

For example, the F-22 Raptor, a 5th-generation fighter still hailed as the world's best, flew in September 1997, five months after the rollout of its EMD (Engineering and Manufacturing Development) unit, and the actual production unit delivered to the Air Force did not appear until 2002. While it was referred to as five months, it essentially required about five years of validation time.

The F-35A also took 10 months from the rollout of its initial production unit, AA-1, to its first flight, and in the case of the Eurofighter Typhoon, delays in parts delivery and assembly issues due to international joint development meant it took over 18 months from final assembly to the first flight.

Furthermore, in the case of our competitor, Sweden's JAS-39 Gripen E, the first production unit rolled out on May 18, 2016, but its first flight was delayed for over a year due to software certification issues.

Among recent fighter jets, the one most similar to the KF-21's "22-day record" is France's Rafale. The B301, the first production model for the French Air Force, was unveiled in September 1998 and flew within about three months, marking a very rapid transition from rollout to flight.

However, while the KF-21 conducted flight tests with prototypes for three years, the Rafale had been undergoing flight tests for over a decade with four prototypes—A, B, C, and M—since 1986. This highlights how mature the KF-21's development and production schedule is and how precisely it has adhered to its timeline.

The KF-21 Block 1 is expected to be officially delivered in the second half of the year following various evaluation tests and acceptance flights. By December 2028, 'Block 2', which includes air-to-ground capabilities, will be developed. Block 2 is expected to be equipped with not only American-made JDAM and SDB guided bombs but also South Korean KGGB guided bombs and the long-range air-to-surface missile (KALCM). Depending on the outcome of export negotiations with the Middle East, it is also expected that the 'Al Tariq' guided bomb from the UAE's Edge Group will be integrated.

This article was automatically translated by AI. There may be errors compared to the original Korean article.
김민석 한국국방안보포럼 연구위원

김민석은 미국 워싱턴에 본사를 둔 에비에이션 위크(Aviation Week)의 한국 특파원이자 한국국방안보포럼(KODEF) 연구위원. 국방일보 등 여러 매체에서 방위산업·국방 전문기자로 활동하고 있다. ‘달란트 투자’, ‘신사임당’, ‘경제한방’, ‘증시각도기’, ‘와이스트릿’ 등 경제·시사 유튜브 채널과 KFN TV ‘리얼웨폰 K’, ‘디펜스 프라임’에 출연해 국제정치와 방위산업 현안을 진단해왔다. 저서로 방위산업 투자 안내서 ‘K-방산에 투자하라’가 있다.